CHAPTER 20:10:22
ENERGY FACILITY SITING RULES
Section
20:10:22:01 Definitions.
20:10:22:02 Content
of notification of intent.
20:10:22:03 Prefiling conference.
20:10:22:04 General
format of application for permit.
20:10:22:05 Application
contents.
20:10:22:06 Names
of participants required.
20:10:22:07 Name
of owner and manager.
20:10:22:08 Purpose
of facility.
20:10:22:09 Estimated
cost of facility.
20:10:22:10 Demand for facility.
20:10:22:11 General
site description.
20:10:22:12 Alternative
sites.
20:10:22:13 Environmental
information.
20:10:22:14 Effect
on physical environment.
20:10:22:15 Hydrology.
20:10:22:16 Effect
on terrestrial ecosystems.
20:10:22:17 Effect
on aquatic ecosystems.
20:10:22:18 Land use.
20:10:22:19 Local land use controls.
20:10:22:20 Water
quality.
20:10:22:21 Air
quality.
20:10:22:22 Time
schedule.
20:10:22:23 Community
impact.
20:10:22:24 Employment estimates.
20:10:22:25 Future
additions and modifications.
20:10:22:26 Nature
of proposed energy conversion facility.
20:10:22:27 Products
to be produced.
20:10:22:28 Fuel
type used.
20:10:22:29 Proposed primary and secondary fuel
sources and transportation.
20:10:22:30 Alternate
energy resources.
20:10:22:31 Solid
or radioactive waste.
20:10:22:32 Estimate
of expected efficiency.
20:10:22:33 Decommissioning.
20:10:22:33.01 Decommissioning of
wind energy facilities -- Funding for removal of facilities.
20:10:22:33.02 Information
concerning wind energy facilities.
20:10:22:34 Transmission
facility layout and construction.
20:10:22:35 Information
concerning transmission facilities.
20:10:22:36 Additional
information in application.
20:10:22:37 Statement required describing gas or
liquid transmission line standards of construction.
20:10:22:38 Gas
or liquid transmission line description.
20:10:22:39 Testimony
and exhibits.
20:10:22:40 Application
for party status.
Declaratory
Ruling: The Public Utilities Commission has filed a declaratory ruling with
the Legislative Research Council in the Matter of the City of Flandreau
Proposed Transmission Line. The City has asked if the proposed project is
within the SDCL 49-41B-2.1 definition of a transmission line and associated
facility, thereby requiring a SDPUC permit. On June 22, 1999, at its regularly
scheduled meeting, the commission determined that the proposed 115kV
transmission line is exempt from its siting jurisdiction because the entire
line will be installed within the existing right-of-way on S.D. Highway 32 and
the Industrial Park Road with the exception of the guying equipment for a
corner pole. Declaratory Ruling EL99-010 dated June 25, 1999.
The Public Utilities Commission has
filed a declaratory ruling with the Legislative Research Council. West River
Electric Association, Inc., requested a ruling from
the Commission regarding its jurisdiction over the siting of a new 115 kV
transmission line near Rapid City. In the ruling, the Commission ordered that
WREA's proposed transmission line is subject to the Commission's siting
jurisdiction. Public Utilities Commission Declaratory Ruling EL00-030 dated
December 14, 2000.