ENTITLED, An Act to
revise certain reclamation surety requirements regarding uranium exploration
and to authorize the Board of Minerals and Environment to adopt rules for the construction,
operation, monitoring, and closure of uranium and other in situ leach mines.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF SOUTH DAKOTA:
Section
1.
That
§
45-6D-19
be amended to read as follows:
45-6D-19.
Prior to the issuance of a uranium exploration operation permit or renewal of a
uranium exploration operation permit the Board of Minerals and Environment shall cause an
inspection to be made of the area proposed to be explored. Based upon this inspection, the criteria
established in § 45-6D-20, and the submitted reclamation plan, the board shall set the level of the
surety necessary to guarantee the costs of plugging all of the proposed test holes and reclamation of
affected public and private lands. The surety shall be filed or deposited with the board before the
issuance of the uranium exploration operation permit in such form as required by the board.
Section
2.
That
§
45-6D-25
be amended to read as follows:
45-6D-25.
The penalty of the required surety shall be in an amount sufficient to cover the cost
of plugging all of the proposed test holes and reclamation as determined pursuant to § 45-6D-19.
Section
3.
That
§
45-6B-81
be amended to read as follows:
45-6B-81.
The board may promulgate rules, pursuant to chapter 1-26, consistent with the
provisions of this chapter, to provide for:
(1)
The procedure for filing and departmental review of mining permit applications;
(2)
The procedure for amending mining permits;
(3)
The procedure for transfer of permits;
(4)
The reclamation of mills proposed to be operated in conjunction with a mining operation;
(5)
The prehearing procedure for determining the type of reclamation to be performed on
affected land;
(6)
The minimum requirements for each type of reclamation;
(7)
The reclamation activities required to be performed concurrent with mining activity;
(8)
The procedure to be followed to address reclamation before or during a temporary
cessation of mining activity pursuant to subdivision 45-6B-3(6);
(9)
The procedure for determining special, exceptional, critical, or unique land in accordance
with § 45-6B-33; and
(10)
The requirements for construction, operation, monitoring, and closure of uranium and
other mineral mines using in situ leach processes.
An Act to revise certain reclamation surety requirements regarding uranium exploration and to
authorize the Board of Minerals and Environment to adopt rules for the construction, operation,
monitoring, and closure of uranium and other in situ leach mines.
=========================
I certify that the attached
Act
originated in the
SENATE as
Bill
No.
62
____________________________
Secretary of the Senate
=========================
____________________________
President of the Senate
____________________________
Secretary of the Senate
____________________________
Speaker of the House
____________________________
Chief Clerk
Senate
Bill
No.
62
File No. ____
Chapter No. ______
|
|
=========================
Received at this Executive Office
this _____ day of _____________ ,
20____ at ____________ M.
By _________________________
for the Governor
=========================
The attached Act is hereby
approved this ________ day of
______________ , A.D., 20___
____________________________
Governor
=========================
STATE OF SOUTH DAKOTA,
ss.
Office of the Secretary of State
Filed ____________ , 20___
at _________ o'clock __ M.
____________________________
Secretary of State
By _________________________
Asst. Secretary of State
|